Wednesday 15 January 2014

Drainage Update - Hole 13

In the last week we have commenced drainage works on hole 13.

Although tree roots have slowed our progress in the last few days we have still managed to installed 80mts of 160mm diameter perforated pipe-work across the 12th fairway. This first section will serve as our mains outlet.

The first inspection chamber is under construction and the digger is now working it’s way across the 13th fairway towards the tree line.

Some pictures of our progress


Pipe being installed across the 12th fairway


First section back filled with gravel and ready for top soil and re-turfing

Digging out the pipe track between the trees on 12th & 13th holes

Main inspection chamber under construction

No comments: