Despite some challenging conditions good progress has been
made on the drainage project on the 4th hole.
We have installed 80mts of 160 mm diameter solid drainage
pipe and begun backfilling the trench, weather permitting we should finish this
section early next week.
While we have the main drainage trench open we intend to install another drain
from in front of the 4th green and connect this into the new
pipe-work.