Wednesday, 6 February 2013

Installation of new phone line cable.


Over the last few days we have begun the installation of a new phone line cable into the Greenkeeping Facilities.

The new cable will connect into the underground junction box beside the 18th tee gate and cross the 17th fairway before its installation into the facility.

This new cable, when installed and connected, will replace the temporary supply from our old facilities.

Unfortunately, the old supply cable is prone to water ingression in a number of different areas and is now beyond economical repair.

Provided the weather doesn’t deteriorate over the next few days, we hope to have the excavations, backfilling and re-turfing completed before the weekend.

Some pictures of our progress.
Excavating across the 17th fairway
Half way point
Backfilling the trench and relaying the turf

No comments:

Post a Comment

Note: only a member of this blog may post a comment.