Update
Good progress has been made in the last few days, we have spread the intermediate layer of grit and the new root-zone has been added.
The grit layer, which is a 2mm to 4mm diameter stone, will stop the root-zone washing down and blocking the perimeter drain and prevent integration of the root-zone with the and sub-base.
Intermediate Layer Completed |
The root-zone is a mix of medium course free draining sand (90% content) and top- soil (10% content).
Turf delivery is expected on Tuesday next week and (weather permitting) Phase 1 should be completed later that day.