Thursday 12 January 2012

Drainage 16th Hole - Update

Drainage 16th Fairway

Since the contractors have returned from the Christmas break they have made excellent progress.
They have now installed and backfilled over 130 meters of pipe-work and provided the weather holds the final 50 meters should be completed by the end of next week. 


Another 6-meter section of pipe being lowered into position
With the new pipework in position backfilling commences