Since the contractors have returned from the Christmas break they have made excellent progress.
They have now installed and backfilled over 130 meters of pipe-work and provided the weather holds the final 50 meters should be completed by the end of next week. ![]() |
Another 6-meter section of pipe being lowered into position |
![]() |
With the new pipework in position backfilling commences |