Greens Facilities Update

Update
I am delighted to announce that the contractors have now completed all interior works in the main storage area and the welfare block.
Once the fire and electrical testing has been completed, the facility will be ready for occupancy.  
Work on the wash-down, fuel and chemical store is almost finished and should be ready for handover by the end of next week.
The forecourt is at present being concreted and the car parking is being made ready for paving.
Some pictures taken earlier today. 
Concreting forecourt
Work progressing on car parking area